Jennifer Porter to Speak at New York CLE Program on State Environmental Quality Review Act (SEQRA) Litigation Issues

Jennifer M. Porter, Esq., a Director in the Gibbons Real Property & Environmental Department, will be a speaker at Lorman’s New York CLE Program SEQRA, on Friday, March 9, 2012 in Latham, New York.

The all-day program will provide a comprehensive overview of New York’s State Environmental Quality Review Act (SEQRA) including specific discussion on regulatory requirements and compliance, the integration of SEQRA with the project review process, cumulative impacts and segmentation and how to use SEQRA to obtain a better project without bankrupting the applicant. Ms. Porter will be part of the afternoon panel and will be discussing SEQRA litigation issues including the statute of limitations, standing to sue, defending or attacking negative declarations and procedural and substantive judicial review.

The program is designed for attorneys, engineers, architects, city and county planners, environmental professionals, presidents, vice presidents, water resource specialists, public works directors, surveyors and project managers. For more information and to register for the program, click here.

Either/Or: Third Circuit Reads Rapanos as Establishing Two Alternative Tests for Federal Regulatory Jurisdiction Over Wetlands

The Clean Water Act regulates the placement of fill into the “waters of the United States.” That term has come to include wetlands -- or at least some wetlands. The Supreme Court’s last attempt, in Rapanos v. United States, to clarify which wetlands fall within the statute’s coverage caused great confusion, as the five Justices who agreed on the judgment (a four-Justice plurality led by Justice Scalia, and Justice Kennedy, who concurred separately) generated two separate tests for jurisdiction. Which test should lower courts apply? In an opinion released on October 31, the Third Circuit said, “both” -- if the wetlands in question satisfy either Justice Scalia’s test or Justice Kennedy’s test, they fall within the statute’s reach.

Justice Scalia’s plurality opinion Rapanos, decided in 2006, took a “wet” view of “waters of the United States,” restricting that term to “relatively permanent” water bodies that formed “geographic features.” Wetlands, under this test, fall within the statute’s scope only if they have “a continuous surface connection” to such bodies of water. By contrast, Justice Kennedy’s “dry” test construed the statute to cover any wetlands that have a “significant nexus” with “waters of the United States, i.e., that the wetlands, alone or in combination with similar lands in the region, significantly affect the chemical, physical, and biological integrity of covered waters.

In United States v. Donovan, the Third Circuit affirmed a district court summary judgment against Delaware landowner David Donovan, who had been fined $250,000 and ordered to remove 0.771 acres of fill that he had placed on his property without obtaining a permit from the Army Corps of Engineers. Donovan argued that the multiple opinions in Rapanos failed to provide a governing legal standard for Clean Water Act jurisdiction, and that therefore pre-Rapanos case law should govern. The Third Circuit disagreed, and, adopting the position taken by the First Circuit and the Eighth Circuit, held that the Corps of Engineers could assert jurisdiction if the wetlands on Donovan’s property met either test set forth in Rapanos. The Court further held that the government’s evidence indisputably showed that Donovan’s wetlands satisfied the “significant nexus” test, and thus did not have to decide whether there was any genuine issue as to whether they satisfied the Rapanos plurality’s test.

Donovan continues an emerging circuit split over how to read Rapanos. Unlike the First, Eighth and (now) Third Circuits, the Seventh Circuit and the Eleventh Circuit have held that Justice Kennedy’s test alone supplies the governing legal standard, applying the Supreme Court’s 1997 decision in United States v. Marks, and concluding that it provides the narrowest grounds for the Supreme Court’s judgment in Rapanos. The Donovan Court and the circuit courts with which it agreed concluded that Marks is inapplicable because either of the two tests in Rapanos could be seen as the narrowest grounds for the judgment -- in some cases, one test would be satisfied but the other would not, and in other cases, the reverse could be true. No circuit court has adopted Justice Scalia’s “wet’ test as the sole governing standard.


John H. Klock is a Director in the Gibbons Real Property & Environmental Department. Paul M. Hauge, an Associate in the Gibbons Real Property & Environmental Department, co-authored this post.

Proposed Legislation Will Require Shopping Center Developments in NJ to Provide Charging Stations for Electric Vehicles

Photo courtesy of Paul Martin Eldridge - freedigitalphotos.netOne of the problems with electric cars (EVs) is - what do you do when the battery runs down? Currently there are 500 charging stations in the United States and 400 of them are in California. In an attempt to address the dead battery problem and encourage purchase of EVs, on March 21, 2011, the New Jersey State Senate introduced Bill S2784 (the “Bill”) which requires owners of shopping center developments to include charging stations. Under the Bill, owners of a “shopping center development” must equip not less than five (5%) percent of the parking spaces for the shopping center development with electric vehicle charging stations. Moreover, such stations must be available for use during the hours of operation of the shopping center development.

The term “shopping center development” is defined by the Bill as “a privately owned and operated commercial development that is or is to be owned and managed as a unit consisting of a building or series of buildings on a common site together with adjacent parking area of no less than 100 parking spaces to which the public is invited.”

The Bill proposes that shopping center owners can recoup “costs of compliance” with the Bill by imposing charges on motorists for EV charging . Therefore, shopping center owners will be required under the Bill to erect signage stating the price per unit of time, unit of voltage, or other measure of usage, as determined by the New Jersey Board of Public Utilities (the “BPU”) to be charged to the motorist for such service. No shopping center owner would be permitted to sell electricity at a price that exceeds the maximum amount per unit set by the BPU. Under the Bill, the BPU is directed to adopt standards for a schedule of prices. A comment period and public hearing on the schedule of prices is required to be held by the BPU before the per unit price is set.

The questions that arise with nearly all new legislation are: (1) when will the law go into effect and (2) who will be required to adhere to the newly promulgated rules and regulations. The Bill as written will contain a four month grace period after its enactment. Therefore, a shopping center constructed prior to the expiration of the grace period will not be obligated to comply with the Bill. The Bill also exempts developers who have filed a site plan application with the applicable municipality prior to the expiration of the grace period. Developers should be aware that the site plan application need only be filed, not approved prior to the expiration of the grace period.

Non-compliance with the Bill will result in penalties to a shopping center owner in an amount of $500 for the first offense and $1000 for all subsequent offenses. The enforcing agency is intended at this time to be the New Jersey Division of Taxation who will have the power to file an action for injunction in the Superior Court to restrain the operations of a shopping center in the event the shopping center owner habitually violates the provisions of the Bill.

The Bill will require developers to evaluate the cost of such “electric vehicle charging stations,” which are defined as an “electric recharging point complete with electric vehicle supply equipment that is capable of providing level 2 charging for plug-in electric motor vehicles,” in connection with their overall budgets for their project. Level 2 equipment which provides charging through a 240 V, AC plug, can take 3 to 8 hours to reach a full charge, adding about 25 miles of range per hour of charging time, depending on the vehicle. Moreover, municipalities, professional planners and land use attorneys may be faced with the issue of whether the Bill impacts municipal parking ordinances and how they are interpreted by local land use boards. For example, if five (5%) of a shopping center’s parking area must be dedicated to EVs, it is conceivable that a municipality may require a developer to provide additional parking spaces for non-electric vehicles to compensate for the lost spaces.

Some other issues that may arise from the Bill are as follows:

  • Developers will need to account for the charging stations in overall square footage of the property in terms of what can be utilized for retail space versus parking and ancillary uses/structures.
  • Traffic experts may have to opine before local land use boards with respect to the impact the charging stations will have on trip generation at the property as vehicles that may not have entered the shopping center in the ordinary course may now enter the site for the purpose of charging their vehicle.
  • The definition of “shopping center development” is fairly vague and simply states that the property be a commercial development with a building or series of buildings with 100 or more parking spaces. Depending on the definition of “commercial development” within a municipality’s zoning ordinance, an argument could be made that the Bill applies to more than just the ordinary retail shopping center, but also to office and/or other commercial developments that normally would not be categorized as a shopping center.

After introduction of the Bill by Senator Linda R. Greenstein (D) of New Jersey Legislative District 14 on March 21, 2011, the Bill was referred to the Senate Environment and Energy Committee. It will be interesting to see if the Bill will move forward as proposed, require amendments, or lack the requisite votes to be passed into law. However, it does seem to be part of a growing “green” trend. Google recently added the location of EV charging stations to its maps and is testing wireless charging stations at its own headquarters in California. The Department of Energy has created a data center on the locations for alternative fuels, including charging stations to serve the plug-in community.

* Photo courtesy of Paul Martin Eldridge - freedigitalphotos.net.


Jason R. Tuvel is an Associate in the Gibbons Real Property & Environmental Department.

New Jersey Time of Decision Rule - The End Nears

New Jersey case law has consistently held that new or modified development ordinance provisions apply to pending land use applications, even if the proposed zoning was specifically introduced to thwart a pending application. This has historically been known as the "time of decision" rule. On May 5, 2011, the time of decision rule will run out of time.

Recognizing the fundamental chilling impact on developers who commit substantial time and money to a project only to have the rules changed by a municipality after the game has already started, the Legislature amended the Municipal Land Use Law to provide that the development regulations in effect on the date of submission of an application govern the review and decision with respect to that application. This legislation was enacted on May 5, 2010, to become effective one year later in order to give municipalities time to revise and update their ordinances.

Accordingly, for those development applications submitted on or subsequent to May 5, 2011, the time of decision rule will no longer apply. Although municipalities will no longer be able to rezone reactively as a substitute for thorough and comprehensive planning or in reaction to public opposition to the application, the question now will be: Is an application that is deemed "incomplete" sufficiently "submitted" to be protected against changes to a municipality's development ordinance?


Douglas J. Janacek is a Director in the Gibbons Real Property & Environmental Department.

Jennifer Porter to Speak at New York CLE Program on State Environmental Quality Review Act (SEQRA) Litigation Issues

Jennifer M. Porter, Esq., an Associate in the Gibbons Real Property & Environmental Department, will be a speaker at Lorman’s New York CLE Program, SEQRA, on Thursday, March 10, 2011, in Latham, New York.

The all-day program will provide a comprehensive overview of New York’s State Environmental Quality Review Act (SEQRA) including specific discussion on regulatory requirements, the integration of SEQRA with the project review process, cumulative impacts and segmentation and the benefits and uses of a generic environmental impact statement. Ms. Porter will be part of the afternoon panel and will be discussing SEQRA litigation issues including the statute of limitations, standing to sue, defending or attacking negative declarations and procedural and substantive judicial review.

The program is designed for attorneys, engineers, architects, city and county planners, environmental professionals, presidents, vice presidents, water resource specialists, public works directors, surveyors and project managers. For more information and to register for the program, click here.

A New Jersey Statute That May Go a Long Way On Your Next Solar or Wind Project!

Experienced New Jersey developers and land use attorneys understand the challenges that face an applicant when the proposed use is not expressly permitted in the municipality’s zoning district where the subject property is located. The challenge is only more complicated if the proposed use involves novel or unfamiliar technology such as renewable energy. However, in New Jersey, the government has been proactive in welcoming renewable energy projects through grants and legislation, making New Jersey definitely the place to be if you want to develop property geared towards the creation of a renewable energy facility powered by solar or wind.

The New Jersey Municipal Land Use Law (“MLUL”) has shed a ray of sunshine onthose developers who wish to construct a solar or wind renewable energy facility. Developers of a solar or wind renewable energy facility must be aware of N.J.S.A. 40:55D-66.11. This section of the MLUL expressly holds that a municipality must permit as-of-right the construction of a renewable energy facility when the subject property is located in one of the municipality’s industrial districts. The only conditions being that the property (or properties) be: (1) comprised of 20 or more contiguous acres; and (2) under common ownership. The statute defines “renewable energy facility” as a “facility that engages in the production of electric energy from solar technologies, photovoltaic technologies, or wind energy.”

Although this statute may seem clear on its face, it does raise some questions for land use attorneys and developers.

  • First, what if a property satisfies the acreage and ownership requirements, does the sole use contemplated for the property need to be a renewable energy facility (i.e. a solar farm)?
  • Second, can a renewable energy facility be deemed an accessory use or structure to a principal use that is pre-existing on the subject property?
  • Third, does the renewable energy facility have to produce energy to a certain amount of users or can it be for a single user?

All of these questions remain unanswered as the development of renewable energy facilities in New Jersey remains in its infancy. This land use attorney foresees litigation over these unanswered questions on the horizon as local land use boards and zoning officials will have to make critical determinations on whether “use variances” are required despite the fact that the MLUL has been amended to facilitate the development of these types of projects.

Land use attorneys should be aware of this recent amendment to the MLUL because it supersedes municipal zoning laws which may not expressly permit renewable energy facilities in the zone where the subject property is located. Developers seeking out properties for their next solar project should always keep in mind that if a property satisfies the criteria set forth in N.J.S.A. 40:55D-66.11, the land use approval process may become a lot easier and possibly more resistant to challenges on an appeal of the approval by a third-party objector.


Jason R. Tuvel is an Associate in the Gibbons Real Property and Environmental Department.

Taking on the NJDOT: Appellate Division Broadens Objector's Ability to Challenge NJDOT Permits

It is not uncommon in New Jersey for businesses to fight tooth and nail to prevent competitors from obtaining development approvals. This month, in In the Matter of the Issuance of Access Conforming Lot Permit No. A-17-N-N040-2007 by the New Jersey Department of Transportation for Block 136, Lots 2 and 3 in Mahwah Township, New Jersey, the Appellate Division dragged the New Jersey Department of Transportation (“NJDOT”) into the fight and provided objectors with another path to delay or even prevent a business competitor from moving into town.

Typically, objections are fought in front of the relevant municipal land use board and later in court. In the Mahwah case, a gas station along Route 17 objected to an application by Pilot to construct a competing service station and convenience store approximately 0.2 miles away on Route 17. In addition to objecting during the Zoning Board of Adjustment hearings, the objector filed a letter and traffic data with the NJDOT objecting to Pilot’s application for a major access permit and waiver for lot frontage pursuant to the State Highway Access Code.

The NJDOT rejected the objector’s submission on the basis that the State Highway Access Code does not allow direct public input and directed the objector to air its grievances during the Zoning Board of Adjustment hearings. Upon the grant of the access permit and waiver, the objector appealed the NJDOT’s decision to the Appellate Division.

The Court began by stating that New Jersey takes “a liberal approach to standing to seek review of administrative actions.” The Court explicitly found that “[t]he competitors of a party who has received a governmental approval required for a proposed business operation also have standing to appeal the approval.” The Court concluded that the objecting gas station owner had standing both as a nearby property owner and as a business competitor.

The Court also concluded that the objector was an “interested person” because it had standing and the issue involved a public interest (i.e. the increase in traffic congestion and risk of accidents). As an “interested person,” the Court found that the Administrative Procedures Act permitted the objector to submit “data, views, or arguments” to the NJDOT for its consideration. Because the NJDOT rejected the objector’s submission, the Court overturned the grant of the permit and waiver and directed the NJDOT to reconsider Pilot’s application in light of the objector’s data, views, and arguments.

This case may have a wide reaching impact on the land use approval process. Besides making the already lengthy NJDOT permitting process even longer and more contentious, the decision and its holding with respect to the Administrative Procedures Act may open the door to making every administrative permitting process into an objecting business competitor’s playground. Although the ability to challenge the issuance of an NJDOT permit may not prevent a business competitor from opening , it will most certainly make the process of obtaining land use approvals longer and more expensive for the applicant.


Jennifer P. Smith is an Associate in the Gibbons Real Property & Environmental Department.

What You Need to Know About Variances and Existing Non-Conformities for Your Next Development Application in NJ

Earlier this month, the New Jersey Appellate Division decided and approved for publication Cortesini v. Hamilton Township Planning Board, a case that addressed the issue of whether a developer must apply for a variance in connection with a pre-existing non-conforming condition created by a prior/non-appealable development approval. The Court’s answer was a resounding “no” based on the facts presented.

In Cortesini, the applicant, Wal-Mart Real Estate Business Trust, applied to the Hamilton Township Planning Board in 2009 for amended site plan approval along with associated bulk variances to renovate an existing Wal-Mart Store. The proposed development contemplated a 3.6% increase in area to the current 156,963 sq. ft. store and the addition of 46 parking spaces. There was a pre-existing non-conforming condition on the property.

In 2001, the initial developer of the shopping center had obtained subdivision approval for the development of the shopping center containing the Wal-Mart store. A year later, Wal-Mart successfully secured a site plan approval that authorized the construction of the Wal-Mart as currently configured. However, the initial approvals failed to identify the need for a parking area setback variance that was clearly required pursuant to the Township’s zoning ordinance.

Wal-Mart’s 2009 development application for the renovation of the existing store was approved by the Planning Board. Thereafter, an objecting third-party appealed the Planning Board’s decision to the Superior Court claiming that the approval was invalid because the applicant did not apply for, and the Planning Board did not grant, a bulk variance authorizing the pre-existing parking area setback non-conformity that would remain in existence at the site. The Superior Court upheld the Planning Board’s decision.

Judge Skillman’s opinion in Cortesini leaves no doubt that a subdivision or site plan approval may be challenged if an applicant fails to obtain a necessary variance. However, as the Court points out, the initial approvals that failed to properly identify and grant the parking area setback variance were not challenged on this issue within the 45-day period following publication of notice of the decision under New Jersey Court Rule 4:69-6.

The third-party objector attempted to circumvent the 45-day appeal period that had long ago lapsed on the 2001 and 2002 approvals by arguing that since Wal-Mart applied for amended site plan approval in 2009 the issue was re-opened. In support of such argument, the objector noted that Wal-Mart was required to obtain a variance authorizing the continuation of the non-conformity of its existing parking lot based on the parking area setback requirement.

The Court’s ultimate rejection of the objector’s argument is predicated on several key facts:

  •  The location of the 46 new parking spaces proposed by Wal-Mart’s 2009 site plan application will not violate the parking area setback requirement;
  • The existing parking spaces that fail to conform with the parking area setback requirement are all located a substantial distance from the parts of the store where the renovations authorized by the amended site plan approval will be constructed;
  • In 2001, the Planning Board noted in its resolution of approval that the layout of the parking area was “consistent with good site design and layout, proper planning, and efficient land use utilization”; and
  • The Planning Board’s resolution of approval in 2009 in connection with the development application supported the findings in the 2001 resolution of approval by stating that the existing parking area, including the nonconformity with the setback requirement is “an existing condition that is functioning well and will not have any detrimental impact to the zone plan.”

Based on these facts, the Court made the following conclusions of law:

  • There is no basis for arguing that a variance is required because the improvements proposed are not within the vicinity of the parking area setback violation and therefore the existing non-conformity will not be enhanced or affected by the 2009 development application;
  • The findings in the Planning Board’s 2001 and 2009 resolutions of approval lead the Court to infer that had the applicant applied for a variance for violating the parking area setback requirement, the Planning Board would have granted the variance; and
  • The objector’s claim that a variance is required authorizing the continuation of the non-conformity of the existing parking lot with the parking area setback requirement constitutes a collateral attack on the 2001 and 2009 development approvals.

The outcome of the Cortesini case provides some clarity to developers and land use attorneys on the grey area of how to deal with pre-existing non-conformities and variance conditions that should have been addressed by prior land use applications.

In this land use attorney’s view, the case stands for the proposition that, so long as the proposed development does not impact the pre-existing condition, the applicant need not apply and obtain a variance for its continuation. However, it would be prudent to ensure that the record at the land use board level clearly covers this point through expert witness testimony. Doing so will allow a court reviewing the record de novo to have factual evidence to support a determination that a variance was not required in connection with the new application.

What should a developer take away from this case? - The importance of zoning due diligence. Zoning due diligence and the review of prior land use approvals will most likely uncover the existence of a pre-existing non-conforming condition. Such knowledge will facilitate not only the presentation of a new land use application, but can be significant in negotiating the value of the subject property because a pre-existing non-conformity can have a negative impact on future development.


Jason R. Tuvel is an Associate in the Gibbons Real Property and Environmental Department.

Howard Geneslaw to Speak at 2010 New Jersey Planning Conference

Howard D. Geneslaw, Esq., PP, AICP, a Director in the Gibbons Real Property & Environmental Department, will be a speaker at the 2010 New Jersey Planning Conference on Friday, November 5, 2010, in New Brunswick, New Jersey. Howard’s topic will be “The Due Diligence Process: Protection for Both the Public and Private Sectors.” Two consulting planners will also be a member of the panel.

The conference, which runs from November 4-5, is jointly sponsored by the New Jersey Chapter of the American Planning Association and by the Edward J. Bloustein School of Planning and Public Policy at Rutgers University. It will include many sessions which relate to a variety of planning topics.

For more information or to register for the conference, click here.

Land Use Public Notices: N.J. Developers/Attorneys Beware!!!

In the most recent case decided in New Jersey on the issue of the adequacy of a land use public notice, the court continued the trend of requiring applicants on development applications to put as much information in their notices as possible to make the general public aware of the nature of the matter under consideration. In Neshanic Coalition for Historic Preservation v. Hillsborough Township Planning Board, Judge Buchsbaum ruled that the applicant’s public notice failed to meet the statutory requirement of setting forth the “nature of the matters to be considered” under the New Jersey Municipal Land Use Law because it omitted the fact that the building to be demolished was located in an historic district.

The court made this ruling despite the fact that the notice had properly identified:

  • the size and location of the property,
  • the dimensional variances being applied for, and
  • the need for a stream corridor waiver.

In analyzing the adequacy of the notice, the court stated that the mention of the building being located in an historic district amounted to “basic information that would help an ordinary person determine whether to object to the application or seek additional information.”

Another fact that the court relied upon in its decision was that the Planning Board of Hillsborough Township did not know that the building was located in a historic district until after taking action to approve the application for site plan approval to construct a 6,700 sq. ft. office building where a single family home built in 1897 currently exists. The Planning Board learned of the historic district issue only when debating the language of the approving resolution.

This case raises some very notable issues for land use attorneys and developers.

  • First, must the zoning district and possibly a historic overlay district (or any overlay district for that matter) be included in the notice for the public hearing?
  • Second, is it the applicant’s responsibility, either through its lawyer or design professional, to alert and educate the municipality of its own zoning information?

The key take-away for this case is that an applicant should always err on the side of caution when drafting its public notice. It is better to be overly inclusive than omit a piece of information that may come back to invalidate the entire proceeding after a time consuming and expensive litigation process. In addition, that over-inclusiveness may at times require the applicant to bring certain zoning issues to a land use board’s attention even where the board’s own professionals have failed to identify the issue. Doing this may save the applicant a lot of time and money in the long run, and could prevent an appeal by an objector.


Jason R. Tuvel is an Associate in the Gibbons Real Property and Environmental Department.

Ye Shall Have No Wine Before It's Time - New York Federal District Court Dismisses Winery's Claims on Ripeness Grounds for Failure to Obtain a Variance Decision or Provide Sufficient Proof That Efforts to Obtain a Variance Would Be Futile

Despite potential substantive merit to Plaintiffs’ federal and state constitutional claims, the Federal District Court of the Northern District of New York in Rivendell Winery LLC v. Town of New Paltz dismissed Plaintiffs’ complaint for lack of subject matter jurisdiction on ripeness grounds as a result of the Plaintiffs’ failure to either obtain a final variance decision or to satisfy the relatively high burden for showing that an application for a variance from the Zoning Board of Appeals would have been futile. The crux of the decision lies in the Court’s reiteration of an important principle that although the success of a land use application may seem doubtful, doubt alone is insufficient to establish that the decision maker has dug in its heels and made certain that the application will be denied. As such, absent facts establishing that a final decision was obtained or that seeking a decision would be futile, constitutionally-based claims or challenges to other pre-decision actions taken by a governmental agency or its officers or employees may not be ripe for adjudication.

In this case, the Plaintiffs, Rivendell Winery, LLC and its principal owner, Susan L. Wine, had sought to reopen a winery and grape-growing business and had acquired two parcels of land in the Town of New Paltz, New York for this purpose. The property was located in the A-1.5 Zoning District which permits agricultural uses as of right. Although the term “agricultural” is not defined under the zoning definition section of the Town of New Paltz Town Code, it is defined elsewhere in zoning provisions as:

[a]ll agricultural operations and activities related to the growing or raising of crops, livestock, or livestock products, and agricultural products, as such terms are defined in or governed by the Agriculture and Markets Law of the State of New York on land qualified under Ulster County and NYS law for an agricultural exemption by the Assessor of the Town of New Paltz.

Plaintiffs submitted an application to the Ulster County Legislature seeking to include the two parcels of land in Ulster County Agricultural District No. 2 and filed an application with the Town Planning Board seeking approval of Plaintiffs’ proposed use of the property within the A-1.5 zoning district.

The Town Building Inspector

Although Plaintiffs had received prior confirmation from the Planning Board Chairperson that the proposed use was “agricultural” and therefore permissible, the Town’s Building Inspector visited the premises and issued a letter to the Planning Board concluding that although the winery is permissible, the retail sale of wine from the house would require a variance from the Zoning Board of Appeals since the Town Code only permits the retail sale of agricultural products grown on the same lot from a road stand. Despite this determination, the Building Inspector later changed his determination finding that the winery was not a permissible agricultural use, and therefore a variance must be obtained from the Zoning Board of Appeals (“ZBA”).

More bad news followed when Plaintiffs withdrew their application after being contacted by a representative of the Ulster County Legislature that suggested they withdraw their application due to public opposition despite a favorable recommendation from the Ulster County Agriculture and Farmland Protection Board. Plaintiffs believed the actions of Building Inspector were the result of undue influence by the Ulster County District Attorney for his own personal and economic reasons and that the action by the legislative representative was motivated by similar reasoning.

The ZBA

Plaintiffs appealed the determination of the Building Inspector to the ZBA. Plaintiffs submitted various documents in support of their appeal, including:

  • a favorable letter from the New York State Commissioner of Agriculture and Markets confirming that the proposed use of the property constituted a “farm operation,”
  • a determination from the Town Assessor that nine acres of Plaintiffs property would qualify for an agricultural exemption and
  • a favorable interpretation from the Ulster County Planning Board.

Despite this documentation, the ZBA unanimously voted to deny Plaintiffs’ appeal. Plaintiffs challenged the ZBA’s decision in an Article 78 proceeding that was unsuccessful at both the Supreme Court and later at the Appellate Division, Third Department.

The Federal Court Filing

Plaintiffs subsequently commenced suit in federal court alleging numerous constitutional violations including:

  • a violation of their federal right to petition the government for the redress of grievances,
  • procedural and substantive due process violations and
  • equal protection violations.

The Defendants, which were comprised of the Town of New Paltz, the Zoning Board of Appeals for the Town of New Paltz and its individual members, as well as Susan Zimet, a representative in the Ulster County Legislature and The County of Ulster, moved to dismiss Plantiffs’ complaint. In light of the legal principles set forth above, the Court granted Defendants’ motion to dismiss since Plaintiffs had failed to apply for a variance from the ZBA to permit the proposed winery and associated sale of wine.

The lesson to be learned from all of this is that just like grapes need to be ripened for wine, so too must claims be ripened prior to being adjudicated. No matter how doubtful a favorable decision may appear to be, in order for claims to be ripe for review, it is critical that a final decision first be obtained or that facts be plead to overcome the high burden of establishing that such an application would have been futile. Luckily for Plaintiffs, all is not lost. The Court dismissed their claims without prejudice to their right to refile in the event they are unsuccessful in their variance application.


Jennifer M. Porter is an Associate in the Gibbons Real Property and Environmental Department.

No Room at the Inn - New York Closes the Door on Illegal Hotels

On July 23, 2010, Governor David Patterson signed into law, legislation that amends the New York State Multiple Dwelling Law to define permanent and transient occupancy. The new illegal hotel law forbids most residential apartment units to be rented out for stays less than 30 days.

This legislation may be a reaction to City of New York v. 330 Continental LLC, a 2009 Appellate Division - First Department holding, which relied on the fact that the critical terms “transient” and “permanent” are not defined in either the Multiple Dwelling Law or the New York City Zoning Resolution. The ambiguity created by this omission has hindered the City of New York from taking enforcement actions against illegal hotels, a problem in New York City, where landlords have been able to convert vacant apartments into temporary housing for tourists, a practice made easier by internet advertising. According to the law’s co-sponsor, State Senator Liz Krueger, over 300 New York apartment buildings had such temporary rental rooms.

Mayor Bloomberg praised the new law, stating:

When housing designated for permanent occupancy is illegally converted into a hotel, unsafe conditions are created, the residential character of City neighborhoods is harmed and the supply of much-needed units of housing is depleted. The bill provides a clear definition of what constitutes transient and permanent occupancy, which will allow City agencies to issue summonses and initiate other enforcement actions against illegal hotels.

Governor Patterson also touted the new law, noting, “By removing a legal gray area and replacing it with a clear definition of permanent occupancy, the law will allow enforcement efforts that help New Yorkers who live in SRO units and other types of affordable housing preserve their homes.”

There was some opposition to the bill, including a demonstration. Those opposing the bill claimed that in a poor economy such rentals were the only way tourists of modest means could afford to visit the city and a source of needed income by desperate apartment owners.

Illegal hotels are widespread and highly profitable. Thus, it remains to be seen what practical impact this legislation will have on the industry. Only time will tell.

Yes, Building in the Highlands Preservation Area is Possible: Court Upholds NJDEP Exemption for Church Project as "Reconstruction" Within "Footprint" of Previous Development

New Jersey’s Highlands Water Protection and Planning Act (Highlands Act), which created and granted substantial powers to a regional Council, has engendered significant controversy, especially with respect to the strict development restrictions it imposes within a statutorily defined preservation area. Certain redevelopment projects, however, are exempt from those restrictions, and a recent Appellate Division upheld the New Jersey Department of Environmental Protection’s (NJDEP) interpretation of key statutory provisions when it determined that a multi-purpose redevelopment project qualified for such an exemption.

Since its enactment in 2004, the Highlands Act has spawned a number of judicial opinions regarding its constitutionality, its retroactivity, and the validity of certain implementation regulations promulgated by NJDEP. (One such case is the subject of a recent post by Gibbons attorney Christina Fullam.)

In In re August 16, 2007 Determination of NJDEP of Exemption, the Appellate Division reviewed NJDEP’s decision to grant Christ Church an exemption from the statute for a project on a 100-acre lot in Rockaway Township that was already the site of office and industrial buildings constructed by a previous owner in the 1990s. The exemption application required NJDEP to determine whether the project qualified for the exemption as a “reconstruction” project that was within 125% of the existing “footprint” of “lawfully existing impervious surfaces” and did not increase that impervious surface by one-quarter acre or more.

NJDEP found that the project satisfied the statutory criteria, and the Township appealed. Applying a doubly deferential standard of review -- because it was reviewing both a final agency determination and an agency’s interpretation of a statute that it is charged with enforcing -- the court upheld NJDEP’s determinations on all three issues:

  • Carefully reviewing the details of the project, the Appellate Division had no trouble upholding, as based on a permissible construction of the statute, NJDEP’s determination that the project was a “reconstruction of any building or structure for any reason.”
  • Similarly, the court upheld the agency’s reading of the term “footprint” as meaning the area covered by all impervious surfaces, rejecting the Township’s argument that the court should look for guidance to NJDEP’s coastal permitting rules, which define “footprint” in terms of structures only.
  • Finally, the court upheld the formula chosen by NJDEP to decide whether the 125% threshold had been exceeded, and the agency’s decision to consider as part of the site’s “lawfully existing impervious surfaces” 20 acres of wetlands that had been filled without a permit in the 1980s because no citation had ever been issued and the fill had later been mitigated and deemed acceptable by the Army Corps of Engineers.

The court added an important suggestion that may have significant implications for future projects: NJDEP should promulgate regulations that define “reconstruction” and “footprint” (and, presumably, other key terms that are not specifically defined in the statute), to “avoid the ambiguity we confronted in deciding this case.” The court concluded,

Such regulations would not only assist future applicants but would prevent judicial review from being dependent on the unique facts presented. The existing regulatory void carries an undue propensity for ad hoc adjudication.


Paul M. Hauge is an Associate in the Gibbons Real Property and Environmental Department.

 

A Redevelopment Designation Worthy of Gallenthin - South Plainfield, NJ, Does it Right

In 2007, just as regulations began to force New Jersey development into its urban areas, where the use of redevelopment is a virtual necessity, the New Jersey Supreme Court decided Gallenthin Realty v. Paulsboro. There, the Supreme Court rejected a municipality's designation of an area in need of redevelopment because the underlying investigation was insufficient under the Local Redevelopment and Housing Law criteria.

In the years since Gallenthin, New Jersey courts have repeatedly rejected redevelopment area designations as not meeting the statutory criteria, thereby stalling redevelopment efforts throughout the State and creating developer angst about the future of development in New Jersey.

But recently, the Appellate Division upheld a city’s designation of a portion of its central business district as an area in need of redevelopment. In Suburban Jewelers, Inc. v. City of South Plainfield, the Court found that the City's preliminary investigation of the area met the substantial evidence burden because it contained specific findings on the condition of each property and detailed how those conditions met the applicable statutory criteria. The report further demonstrated how those conditions were detrimental to health, safety, and welfare and to surrounding properties.

This decision offers some guidance as to the necessary elements of a redevelopment investigation and gives the real estate industry a glimmer of hope that redevelopment remains a viable mechanism in New Jersey in the post-Gallenthin world.


Michael Miceli is an Associate in the Gibbons Real Property and Environmental Department.

Time-out: Pennsylvania Passes Permit Extension Act

Last week, Governor Rendell signed the Permit Extension Act ("Act") into law as part of the approval of the budget, breathing life into expired and expiring permits and the development projects they represent.

The Act, found at pages 99-110 of the budget bill, extends the expiration date of many governmental approvals, permits and agreements, including building permits and construction permits, relating to construction and development projects.

What Permits Does It Affect?

The Act applies to certain permits issued under more than thirty statutes, including:

The Act also applies to certain permits issued to condominiums, cooperatives and planned communities.

The Act Does Not Apply to All Permits

The Act does not apply to other statutes, including the:

The Act also does not apply to permits with expiration dates determined by federal law, or to administrative consent orders and enforcement actions for a permit subject to the extension period.

How Long is a Permit Extended?

Under the Act, a permit granted under an applicable statute and having an expiration date after December 31, 2008 may have its expiration date extended until July 1, 2013, regardless of whether the permit was issued before or after the extension period. The Act does not shorten the life of a permit with an expiration date after July 1, 2013.

How Can You Find Out If the Act Applies to Your Permit?

The permit holder can request verification, subject to a fee, from the issuing agency of the existence of a valid permit and its expiration date, but must identify the permit in question and its anticipated expiration date. The issuing agency must tell you in writing within 30 days of receiving your request:

  1. whether you have a permit;
  2. its expiration date; and
  3. stating any issues related to the validity of the permit.

Except in Philadelphia and Pittsburgh, the failure of the issuing agency to respond within 30 days will result in the "deemed affirmation of the existence of the [permit] and the expiration date set forth in the request."

In the City of Philadelphia, in order to exercise its right to extend the permit under the Act, the permit holder must provide the issuing agency with notice of its intent to extend the permit and pay the agency a fee equal to fifty percent of the original application fee, not to exceed $5000. Elsewhere, the issuing agency may charge a fee up to twenty five percent of the original application fee, but no more than $5000, to extend the Permit.

Permits granted pursuant to the MPC are protected from changes in a "zoning, subdivision or other governing ordinance or plan," such that those changes will not affect the permit holder’s right to begin or complete the activities authorized by the permit during the extension period. The extension period is further extended for the length of litigation, including appeals, concerning permits issued under the MPC that prevent the completion of the work authorized by the permit.

The Act brings Pennsylvania into line with New Jersey which enacted its own permit extension legislation in 2008. The Act gives needed flexibility and time to developers who may be facing financial challenges in the current economy. At a minimum, permit holders should consider verifying the viability of permits, and extending them as required, now so they will be in a position to proceed when market conditions warrant.


Alfred R. Fuscaldo is a Director in the Gibbons Real Property and Environmental Department.